Digital Realty's $3 billion data center in Georgia is stopped after finding dangerous white phosphorus at an old army dump.

TroubleRead the original at Benzinga
Bad for DLR

Digital Realty halted work after workers found white phosphorus and expects to spend over $100 million cleaning up the former dump site. It says only 5 drums were found and plans to seal the area under concrete, but the hazard and work stoppage still threaten the project.

DLR · Digital Realty Trust Inc.

AI read · Bad for DLR

The AI's read

This could delay the planned facility and add cleanup work before it can open. Digital Realty says the 5 drums were fewer than might have been found and plans to cover the area with concrete. Nearby residents report blasting damage, but the company says its review found the site work did not cause it.

Get alerts for DLR

Follow Digital Realty Trust Inc. (DLR) free. When we publish a story about it, you get the plain-English explanation as an alert.

Get alerts for DLR
Free on the App Store and Google Play, or on the web.